Dodge Church
- Estacada, Oregon
Overview
STATUS: Completed 2023
In the wake of the 2020 Riverside fire — which burned 138,000 acres in Clackamas County Oregon — the Dodge Community Church was burned to the ground. Carpentry Plus was able to re-purpose remaining material from a previous project to rebuild the church at a significant savings to the congregation. We are proud of the part we were able to play in helping rebuild our community, that was so significantly impacted by the 2020 wildfires.
Specifications
ROLE: Supply-Install of Mass Timber
Design Team
SQUARE FOOTAGE: 2,500
HEIGHT: 1 story
MATERIAL: Cross-Laminated Timber roof system with tension rods
DEVELOPER: Dodge Church
ARCHITECT: Orange Wall Studios
STRUCTURAL ENGINEER: Stonewood Engineering
GC: Carpentry Plus Inc
Suppliers: Structurlam